Sun-Lite Installation Guide

Sun-Lite FRP Roofing — Installation Guide

Follow these guidelines to ensure a weather-tight, long-lasting Sun-Lite FRP roof installation. Always refer to the full Installation Guide PDF for detailed drawings and specifications.

Step 1 — Site Preparation & Material Check

  • Verify all structural purlins are correctly aligned, levelled, and fixed according to the engineer's design
  • Check purlin spacing does not exceed 1,200mm (or as specified by engineer)
  • Ensure the roof slope is a minimum of 10% (approx. 6°)
  • Clear all debris, swarf, and drill filings from purlins before laying sheets
  • Inspect all Sun-Lite sheets for damage, delamination, or surface defects before installation
  • Prepare all necessary flashings, trims, and sealants in advance
  • Mark purlin locations clearly for accurate fastener placement
  • Check weather forecast — avoid installation during heavy rain or extreme heat
  • Ensure adequate scaffolding and safe access is in place
  • Pre-drill all holes in FRP sheets before positioning on the roof

Step 2 — Sheet Cutting & Pre-Drilling

  • Cut sheets using a fine-tooth saw blade (carbide-tipped or diamond blade) at low speed to avoid chipping
  • Support sheets fully during cutting to prevent vibration cracks
  • Use a hole saw or stepped drill bit for round penetrations (e.g., vent pipes)
  • All holes must be minimum 2mm larger than the fastener shank diameter to allow thermal movement
  • De-burr all cut edges to remove sharp fragments
  • For sheet end overlaps, drill oval ( slotted) holes to allow expansion
  • Keep cut edges clean — do not leave exposed FRP edges overnight
  • Apply acrylic or epoxy sealer to cut edges to prevent moisture wicking
  • Label sheets in sequence of installation to maintain sheet alignment
  • Cut all sheets before placing any sheets on the roof structure

Step 3 — Sheet Placement & Alignment

  • Start installing from the ridge (top) and work downwards to the gutter
  • Place the first sheet at one end of the roof, ensuring it overhangs the gutter by a minimum of 50mm
  • Maintain the recommended side lap of 1.5 corrugations minimum (full corrugation preferred)
  • Align sheets straight — a string line along the gutter edge helps maintain accuracy
  • Do not walk on unsupported sheets — use crawl boards or platforms spanning minimum 3 purlins
  • For long roof spans requiring end laps, maintain a minimum 150mm end lap (200mm for slopes below 10%)
  • Ensure end laps fall on top of a purlin — never mid-span between purlins
  • Stagger end laps in alternate rows to avoid a continuous joint line
  • Position FRP sheets with the UV-protected film side facing upwards (film label indicates top surface)

Step 4 — Fastening

  • Use only corrosion-resistant fasteners (stainless steel or hot-dip galvanised) with EPDM sealing washers
  • Fasten at the crown (top) of the corrugation — never in the trough
  • At end spans: fasten at every corrugation, approximately 300mm pitch
  • At internal spans: fasten at every 2nd or 3rd corrugation, approximately 450–600mm pitch
  • Side laps: fasten at every 2nd–3rd corrugation along the overlapping side lap
  • Do NOT over-tighten fasteners — the EPDM washer should be just fully compressed, not deformed
  • Ensure the fastener is perpendicular to the roof surface (not angled)
  • All fasteners must engage a minimum 50mm into the structural purlin
  • Check fasteners after the first round of installation for correct torque
  • Replace any damaged or corroded fasteners immediately

Step 5 — Sealing & Flashing

  • Apply neutral-cure silicone sealant along the top sheet's side lap corrugation before placing the overlapping sheet
  • At end laps, apply sealant to both overlap surfaces and the top of the purlin before joining
  • Use butyl rubber sealer tape at all fastener locations under the EPDM washer for extra weather protection
  • For roofs below 10% slope, apply sealant to all laps, end laps, and penetration joints
  • Install pre-formed ridge flashings at the ridge — secure one side to the FRP crown, leave the other side loose to allow movement
  • Use gable end trims to close the roof edges neatly
  • For wall penetrations, install counter flashings with a minimum 100mm overlap onto the FRP sheet
  • Apply sealant around all penetration flashings — check seals after first rainfall

Step 6 — Completion & Inspection

  • Inspect all fasteners for correct torque and sealing washer compression
  • Check all side laps and end laps for complete sealant coverage
  • Verify all flashings and trims are properly secured and sealed
  • Remove all drill swarf, cutting debris, and loose material from the roof surface
  • Check the gutter and surrounding area for fallen debris or fastener remnants
  • Inspect during first rainfall to identify any leaks at laps, flashings, or fasteners
  • Address any leaks immediately with additional sealant — do not allow water to pond
  • Remove the UV-protective film from sheet surfaces after installation is complete (if still in place)
  • Do not apply harsh chemicals or abrasive cleaners to FRP sheets
  • Keep the roof surface clean — remove debris, leaves, and standing water promptly

Important Safety Notes

  • Always use appropriate personal protective equipment (PPE): safety harness, non-slip footwear, gloves, and eye protection
  • Ensure scaffolding and edge protection is in place before commencing work at height
  • FRP sheets can be slippery when wet — do not walk on sheets unless absolutely necessary and with proper safety measures
  • Do not use FRP sheets as a working platform or storage area during installation
  • Dispose of all cut FRP fragments and packaging responsibly — follow local waste management regulations

Downloads

Full Installation Guide

Complete step-by-step with diagrams

Download PDF

Sun-Lite Brochure

Product details and specifications

Download PDF

Industrial Profiles

Full profile range catalogue

Download PDF

© 2018 Space (Asia) Sdn. Bhd. All Rights Reserved.